U-Pave completed a full asphalt removal and repaving program, delivering a smooth, durable, and traffic-ready surface tailored for a high-use storage facility. The work included controlled saw-cutting at tie-in locations, removal of existing pavement, base restoration, and placement of a new commercial-grade asphalt surface designed for long-term performance.

All work was executed in accordance with project requirements, with a focus on clean transitions, proper compaction, and a consistent finished appearance across the site.

Scope of Work Summary

  • Saw-cutting at designated asphalt tie-in locations
  • Removal of existing asphalt pavement to design depth
  • Loading, hauling, and off-site disposal of removed materials
  • Supply, placement, and compaction of granular base course
  • Application of emulsified asphalt bonding tack coat
  • Supply, placement, and compaction of new asphalt surface course
  • Final site reconciliation and cleanup

 

Project Quantities at a Glance

Work Item Material / Description Average Thickness Area
Asphalt Removal Existing asphalt pavement 275 mm 4,575 m²
Granular Base Course 20 mm Granular Base 50 mm 4,575 m²
Tack Coat SS-1 Emulsified Asphalt 4,575 m²
Asphalt Surface Course Asphalt surface course (ACP) 75 mm 4,575 m²

Result

A renewed asphalt surface delivering improved durability, smoothness, and long-term serviceability—completed with clean tie-ins, consistent compaction, and a professional finish suitable for commercial operations.

Legal Description: Plan 8722091 Blk 1 Lot 14A

Project Overview

Location

5403 136 Ave NW, Edmonton, AB T5A 4W1


Project Type

Full Asphalt Removal and Repaving Program


Client

Access Property Development


Status

Substantial Completion (1-year Warranty in effect)